Add an Operating Schedule

  1. Open up the area you are creating a schedule for and select the “Schedules” tab at the top of the page.

  2. Create your schedules by selecting the “Operating Schedule” field and locating the “Add New” button.

  3. Operating schedule runs on a per year value (8760 hours is the max input).

  4. The first schedule created will be the default across the project.

  5. You can set different schedules for different areas.

Add a Rate Schedule

  1. Open up the area you are creating a schedule for and select the “Schedules” tab at the top of the page.

  2. Create your schedules by selecting the “Rate Schedule” field and locating the “Add New” button.

  3. Rate schedule example: $0.13/kWh is input as .13

  4. The first schedule created will be the default across the project.

  5. You can set different schedules for different areas.

Bonus: Add Heating and/or Cooling Systems

  1. Add any heating and cooling systems to the area. Your final calculations will not be affected in any way if this information is not available.

  2. The first heating or cooling schedule created will be the default across the project.

  3. You can set different heating and cooling schedules for different areas